|
|
Rate
Schedules and Policies
RSP
N-13
Rate
Schedules and Rate Application Guidelines
Large
Industrial Rate Schedule - Cont'd
Schedulable Energy (continued)
Customers who fail to interrupt will be billed an additional
charge which is the higher of:
(i) two times the monthly demand charge per kilowatt for the
Large Industrial rate classification multiplied by the kilowatts
that were interrupted plus any incremental cost of supplying
the energy, or
(ii) the costs incurred by Maritime Electric for replacement
energy to supply financially firm export obligations.
The price is based on Maritime Electric's incremental cost
of providing such energy. Incremental cost is defined as Maritime
Electric's incremental generation or purchased power costs
after supplying in-province firm load and other firm supply
commitments.
Pricing
of Schedulable Energy
Schedulable Energy price will be:
On peak price = incremental cost during on peak hours +1.23¢/kWh.
Off peak price = incremental cost during on peak hours +0.41¢/kWh.
The on peak period is defined as 0800 to 2400 hours Atlantic
Prevailing Time on all weekends, except statutory holidays
in Prince Edward Island. All other hours are considered to
be off peak.
Maritime Electric will provide a week ahead forecast and day
ahead firm quotes of the one and off peak prices to be paid
by the Customer. When Maritime Electric has insufficient generation
to supply its loads, the price of Schedulable Energy will
be quoted and updated on an hourly basis.
Schedulable Energy Customers can arrange for a third party
outside of Prince Edward Island to supply energy to Maritime
Electric. In such an event, Maritime Electric would pay the
supplier 0.06¢/kWh less than the incremental cost used
in determining the price of Schedulable Energy and the Customer
would still pay Maritime Electric the full price of Schedulable
Energy including the adders.
Energy Cost Adjustment Mechanism: This rate is subject to the Energy Cost Adjustment Mechanism
RSP
N-14
Rate
Schedules and Rate Application Guidelines
Large Industrial Rate Schedule - Cont'd
Rental
Charges
At the customer's request, Maritime Electric will supply,
own and maintain the substation facilities from the high voltage
switches to the low voltage terminals of the step-down transformers,
provided such transformation satisfies Maritime Electric Standards.
The charge for such rental facilities is 15/6%
per month of the installed costs. The Customer will supply
the low voltage switch gear, concrete substation foundation
pads and necessary protective fencing.
Losses Charge
At the discretion of Maritime Electric, electricity may be
supplied at a primary service voltage between 4 kV and 25
kV. In such cases, the monthly demand and energy consumption
will be increased by 1½% to compensate for transformation
losses.
Transformation
Charge
When a customer is provided service at voltages less than
69 kV, the customer will also be charged an "equivalent
kVA rental" charge equal to 15/6%
per month of the costs of the equivalent substation kVA utilized
by the Customer's electrical load. The equivalent kVA charge
is the Customer's kVA demand multiplied by $1.15 per kVA per
month.
Contracts
A customer supplied at the Large Industrial Rate is required,
and is deemed, to have entered a firm contract providing for
the payment of the rate, for an initial term of five (5) years,
in the case of a customer considered by Maritime Electric
to be a new customer, and for an initial term of one year
for a customer considered by Maritime Electric to be an existing
customer. The contract will continue thereafter on a firm
basis subject to termination by either the customer or Maritime
Electric at the end of the initial term, or any date thereafter
by either party giving at least twelve month's notice in writing.
When a Customer's operations are jeopardized because of a
failure of its electricity generating equipment, the Customer
can apply to suspend any portion of its curtailable power
contract and/or firm up all or part of interruptible purchases
for a period of at least six months and not more than one
year.
Metering
The metering point shall be at or near the transmission line
terminals (69 kV).
Energy Cost Adjustment Mechanism: This rate is subject to the Energy Cost Adjustment Mechanism
|
|